Analisis Penjadwalan Proyek Perumahan Bersubsidi Lembah Berkah pada PT Mirai Aldyatama Graha dengan Metode Program Evaluation and Review Technique dan Critical Path Method

Authors

  • Puspita Sudi Ariati Universitas Slamet Riyadi
  • Sunarso Sunarso Universitas Slamet Riyadi

DOI:

https://doi.org/10.54259/manabis.v5i3.9004

Keywords:

Project Scheduling, PERT, CPM

Abstract

Increasing business competition requires companies to improve the effectiveness of operational management, including construction project scheduling. Project completion delays may result in losses for both the company and its customers. Based on data from PT Mirai Aldyatama Graha, most projects experienced delays compared to the planned schedule. This study aims to analyze the scheduling of the Lembah Berkah Subsidized Housing Project using the PERT and the CPM. The research employed qualitative and quantitative data collected through interviews, observations, and documentation from both primary and secondary sources. The PERT analysis indicated a 93.57% probability of project completion if the project was targeted to be completed within 150 days, with the critical path consisting of activities A, B, C, D, F, H, and J. The CPM analysis showed that the project could be completed in 137 days at a normal cost of IDR 2,500,000,000. Full crashing reduced the project duration to 108 days at a cost of IDR 3,022,410,000, while the least-cost strategy achieved the same duration with cost savings of IDR 294,149,998 and identified the critical paths as A, B, C, D, F, H, J and A, B, C, E, G, H, and J. The findings indicate that the PERT and CPM methods effectively optimize project scheduling, while the least-cost strategy is a more efficient acceleration alternative because it achieves the same target duration at a lower cost.

Downloads

Download data is not yet available.

References

Adrianti, S., Hafiz, H., Safitri, W., dan Huda, M. 2024. "Analisis Penjadwalan Proyek Pembangunan Saung Serbaguna di Cikarang Menggunakan PERT dan CPM". Jurnal Ekono Insentif. Vol. 18, No. 1, April, hlm. 62-73.

Aprillia, S. C., dan A’yun, Q. Q. 2023. "Optimalisasi Biaya dan Waktu Pelaksanaan Pembangunan Rumah Tinggal di Kecamatan Rantau Pulung Kutai Timur Menggunakan Critical Path Method (CPM) dan Program Evaluation and Review Technique (PERT)". Jurnal Ilmiah Matematika. Vol. 2, No. 1, Maret, hlm. 11-24.

Asba, A., dan Altrarans, I. 2024. "Optimalisasi Pelaksanaan Proyek Kontruksi dengan Menggunakan Metode PERT dan CPM (Studi Kasus Peningkatan Jalan Toloa Kota Tidore Kepulauan". Jurnal Akrab Juara. Vol. 9, No. 1, Februari, hlm. 1-12. Yayasan Akrab. Pekanbaru.

Assauri, S. 2016. Manajemen Operasi Produksi. Raja Grafindo Persada. Jakarta.

Aulia, S., dan Cipta, H. 2023. "Network Planning Analysis Using CPM and PERT Methods on Optimization of Time and Cost". Jurnal dan Penelitian Teknik Informatika. Vol: 7, No. 1, Januari, hlm. 171-177.

Heizer, J. H., Render, B., dan Munson, C. 2017. Operations Management: Sustainability and Supply Chain Management. Edisi Keduabelas. Pearson. Boston.

Hidayanto. 2021. Manajemen Proyek. Hei Publishing Indonesia. Padang.

Jouda, M. A., dan Shiker, M. A. K. 2024. "Comparing the Effectiveness of PERT and CPM Techniques in a House Construction Project: A Case Study". Journal Européen Des Systèmes Automatisés. Vol. 57, No. 3, Juni, hlm. 781-785.

Julyanthry, Siagan, V., Asmeati, Hasibuan, A., Simanullang, R., dan Pandarangga, A. P. 2020. Manajemen Produksi & Operasi. Yayasan Kita Menulis. Medan.

Leimena, I. M. dan Fahmi. 2024. "Percepatan Waktu Menggunakan Metode CPM dan PERT pada Proyek Instalasi Pipa dan Mesin Pompa Swimming Pool Buin Batu School". Jurnal Ilmiah Teknologi Infomasi Terapan, Vol. 11, No. 1, Desember, hlm. 55-64.

Lubis, L. R., Umari, Z. F., Kristi, K., dan Akhirini, A. 2023. "Analisis Penjadwalan Waktu Menggunakan Metode CPM dan PERT pada Pembangunan Gudang Dexa Medica Palembang". Jurnal Teknik Sipil Lateral. Vol. 1, No. 2, hlm. 21-30.

Pratama, A. Y., dan Kartini, I. A. N. 2020. "Analisis Perencanaan dan Penjadwalan Proyek Pembangunan Rumah Kos Menggunakan Network Planning PERT dan CPM Di Kota Surabaya". JEM17: Jurnal Ekonomi Manajemen. Vol. 5, No.1, Mei, hlm. 19-32.

Project Management Institute, P. 2021. Guide to the Project Management Body of Knowledge (PMBOK guide). Independent Publisher Group. Chicago USA.

Purnomo, K. B., dan Ardan, M. 2025. "Evaluasi Penerapan Teknik Crashing dalam Manajemen Waktu Pembangunan Rumah Subsidi Metode CPM dan PERT (Studi Kasus Rumah Pondok Alam Desa Sigara-Gara)". Jurnal Teknik Sipil. Vol. 14, No. 1, April, hlm 171-181.

Rahlahallo, F. N., Jaya, F. H., dan Tukimun. 2024. Manajemen Proyek. Sulur Pustaka. Yogyakarta.

Rakasyiwi, G. R., Witjaksana, B., dan Tjendani, H. T. 2022. "Analisis Penjadwalan Proyek Menggunakan Metode Jalur Kritis – Studi Kasus: Proyek Pembangunan Rumah Bersubsidi di Perumahan Hill Mulya, Kota Samarinda". International Journal on Advanced Technology, Engineering, and Information System. Vol.1, No. 4, November, hlm 73-88.

Rani, H. A. 2016. Manajemen Proyek Konstruksi. Deepublish. Yogyakarta.

Rani, H. A., Maina, F. F., Aqsha, M. S., dan Mubarak, M. H. 2024. "Time and Cost Efficiency Analysis of Aceh Tengah Regency Pom Workshop Project: A Critical Path Method Approach". International Journal of Engineering Science Technologies. Vol. 8, No. 3, May, hlm. 34-46.

Sahid, Muh. N. 2017. Teknik Pelaksanaan Konstruksi Bangunan. Muhammadiyah University Press. Surakarta.

Santosa, B. 2023. Manajemen Proyek Konsep & Implementasi. Graha Ilmu. Yogyakarta

Santoso, F. W., Handayani, F. S., dan Setiono. 2025. "A Comparative Analysis of the CPM and PERT Methods in Project Time Management for a High-Rise Building Construction Project in Yogyakarta". Sustainable Civil Building Management and Engineering Journal. Vol. 2, No. 2, April, hlm. 1-13.

Siregar, A. A., dan Lubis, K. 2025. "Analisis Manajemen Pengendalian Waktu dengan Pendekatan Metode CPM & PERT pada Proyek Peningkatan Jalan Alternatif Medan-Brastagi-Kutalimbaru". Jurnal Teknik Sipil. Vol. 17, No. 1, April, hlm. 69-76.

Sugiyono. 2023. Metode Penelitian Kuantitatif Kualitatif dan R&D. Edisi Kedua. Alfabeta. Bandung.

Windihastuty, W., Rony, M. A., dan Putra, B. C. 2024. Manajemen Proyek Perangkat Lunak. Deepublish Digitall. Yogyakarta.

Downloads

Published

2026-09-10

How to Cite

Puspita Sudi Ariati, & Sunarso, S. (2026). Analisis Penjadwalan Proyek Perumahan Bersubsidi Lembah Berkah pada PT Mirai Aldyatama Graha dengan Metode Program Evaluation and Review Technique dan Critical Path Method. MANABIS: Jurnal Manajemen Dan Bisnis, 5(3), 694–704. https://doi.org/10.54259/manabis.v5i3.9004